Arbitral Damages Require Reasons: Delhi High Court Sets Aside ₹4 Crore Compensation

Candour Legal | Arbitration & Commercial Litigation | Legal position reviewed 23 November 2026

An arbitral tribunal may estimate compensation where a loss or entitlement is established but exact quantification is difficult. It must nevertheless explain why the evidence supports the amount awarded. In Intech Brinechem Ltd. v. De Dietrich Process Systems India Pvt. Ltd., O.M.P. (COMM) 155/2024, decided on 28 October 2026, the Delhi High Court set aside the ₹4 crore compensation component of an award because the quantum was not supported by a discernible reasoning process. The Court also set aside EUR 8,000 in Paris litigation costs; the balance of the award was left undisturbed.

This distinction is relevant to in-house counsel, engineering and procurement contractors, infrastructure project companies and arbitration practitioners dealing with partially performed contracts. The case concerns the sufficiency of reasons for quantum, not a general licence for Section 34 courts to revalue claims.

1. The contract and competing accounts of non-performance

The dispute arose from an agreement dated 3 May 2022 for detailed engineering, supply of Outside Battery Limits equipment and allied services for a bromine plant in the Rann of Kutch, Gujarat. The total contract value was approximately ₹53 crore. Intech Brinechem paid an advance of ₹5.30 crore against a performance bank guarantee.

Intech alleged that engineering drawings and designs were defective, that repeated requests for corrections went unaddressed and that the contractor abandoned the work. The contractor disputed that account, attributing delay and non-execution to missing statutory approvals, land availability and further payments on the employer’s part. The court recorded the competing positions; they should not be presented as independent findings of wrongdoing by either company.

Following the invocation of the performance bank guarantee, the dispute proceeded to arbitration. The contractor advanced counterclaims for work undertaken and associated losses.

2. What did the arbitral tribunal decide?

The arbitral award dated 2 February 2024 attributed responsibility for the contractual breakdown to both parties. It accepted that certain preliminary engineering work had been undertaken, while rejecting aspects of the counterclaim for want of adequate evidentiary support. The tribunal nonetheless assessed ₹4 crore as compensation on an estimated basis, with interest, and addressed costs of proceedings in Paris.

The controversy before the High Court was whether acceptance of some work, without a defensible valuation bridge, could sustain this particular amount. Proof that drawings or process sheets existed was not necessarily proof of their contractual value.

3. What is required of a reasoned damages assessment?

Section 31(3) of the Arbitration and Conciliation Act, 1996 generally requires an arbitral award to state the reasons upon which it is based, subject to statutory exceptions. Section 34 preserves a limited judicial challenge mechanism, including the ground of patent illegality appearing on the face of a domestic award in the circumstances provided by the Act.

A reasonable estimate is not automatically invalid. Where valuation is imperfect, the tribunal may examine the material before it and arrive at a supportable approximation. It must, however, disclose enough of its reasoning for the parties and a reviewing court to understand how the figure follows from the evidence.

  • Entitlement: identify the contractual or legal foundation for compensation.
  • Performance or injury: identify the work completed or loss established.
  • Evidence: connect accepted deliverables, project records, certifications, correspondence or expert material to the claim.
  • Valuation: identify the rate, milestone, cost base, approximation method or other rational basis used.
  • Explanation: explain material uncertainties and why the resulting amount is justified.

4. Why the Delhi High Court interfered with ₹4 crore

The High Court observed that the tribunal had relied on certain accepted layout plans and process data sheets to find that some preliminary engineering work was undertaken. What was missing was a reasoned connection between those materials and ₹4 crore. The amount appeared as an estimate without adequate explanation of the underlying methodology.

The legal defect was therefore not that the tribunal chose a large amount or that the judge would have preferred a different valuation. The defect was the absence of intelligible reasons for that amount. A Section 34 court cannot ordinarily conduct a fresh merits appraisal; it can nevertheless intervene when a component of the award suffers from a statutory infirmity.

5. Why the Paris costs component was set aside

The tribunal had also allowed EUR 8,000 arising from litigation before the Commercial Court in Paris. In examining that direction, the High Court considered the Paris order and the later encashment of the performance bank guarantee. It found that the award did not explain a sustainable basis for recovering in arbitration the costs that the Paris court had directed the contractor to pay to the other side and the bank.

Accordingly, the Court set aside the EUR 8,000 component as well. References in reporting to approximately ₹7 lakh concern the rupee equivalent of these Paris costs, not a further distinct award of ₹7 lakh.

6. What the Court did—and did not—set aside

At paragraphs 54–57 of the judgment, the Court allowed the Section 34 petition in part. It set aside the ₹4 crore estimated compensation component and the EUR 8,000 Paris litigation costs. It expressly left the remaining findings and directions of the arbitral award undisturbed.

The decision must therefore not be reported as wholesale annulment of the award, or as judicial reassessment of the contractor’s complete entitlement. The judgment itself is dated 28 October 2026; the electronic signature visible on the copy is dated 6 November 2026. Those are distinct dates.

7. Practical implications for EPC and project disputes

In engineering, procurement and construction disputes, the presence of some drawings or preparatory deliverables may demonstrate activity but may leave substantial questions about contractual value. A party seeking money for partially performed work should formulate whether its demand is for an agreed milestone payment, damages, restitution or another recognised basis, and then demonstrate the amount by evidence appropriate to that basis.

For instance, if a contract contemplates design milestones but only preliminary sheets are available when the project is terminated, counsel should identify which milestones were achieved, whether approval or acceptance was required, and what the contract provides for partial performance. The tribunal should not simply adopt a percentage of the overall contract price without explaining why that percentage reflects the work proved.

Claimants should preserve deliverable registers, approvals, milestone certificates, tender costings, invoices, contemporaneous correspondence and any expert valuation. Respondents should direct objections to concrete gaps in proof or methodology rather than merely assert that an amount is excessive.

8. Candour Legal Insight: an evidentiary chain, not a headline number

The most useful discipline for commercial arbitration is to separate four questions: What is the legal entitlement? What was actually done or lost? What evidence establishes it? How does that evidence produce the figure claimed? These questions protect the integrity of the claim and the award. They also reduce the risk that a reviewing court will encounter a result without an intelligible route to it.

The lesson is not that every arbitral award needs elaborate financial modelling. It is that the reasoning must be proportionate to the disputed component and sufficient to demonstrate that compensation is an assessment, not a guess.

9. Checklist for arbitration teams

  • Specify the legal basis separately for contractual price, damages, reimbursement and costs.
  • Correlate work products or losses with contractual milestones and contemporary records.
  • Prepare a reproducible methodology for estimated quantum.
  • Explain limitations in available evidence and the assumptions adopted.
  • Identify orders governing costs incurred in related foreign proceedings.
  • In a Section 34 challenge, formulate an available statutory ground rather than inviting routine merits review.
  • Check the operative paragraph carefully: partial setting aside does not invalidate every part of an award.

Questions frequently asked by businesses

Can an arbitrator award estimated damages in India?

Yes, where justified by the circumstances and supported by evidence and intelligible reasons. Estimation without a reasoned basis is vulnerable to challenge.

Can a Section 34 court recalculate compensation?

Section 34 is not a regular appeal on facts or valuation. The court may interfere only within the applicable statutory grounds; it does not ordinarily substitute its preferred damages figure.

Was the entire Intech Brinechem arbitral award set aside?

No. The High Court set aside the ₹4 crore estimated compensation and EUR 8,000 Paris litigation costs components, and left the remainder undisturbed.

Primary judgment and related resources

Enquiries concerning commercial arbitration and litigation

For a case-specific question concerning contractual claims, arbitral awards or judicial challenges, Candour Legal may be contacted using the channels below. Please do not send confidential documents before engagement terms are agreed.

Sending an enquiry does not by itself establish an advocate–client relationship.

Source and review note: Judgment dated 28 October 2026, paragraphs 1–13, 27–36, 38–45 and 50–57; legal verification on 23 November 2026. The Delhi High Court’s official judgment listing was checked. No later stay or appeal was identified in the searches conducted; that statement is not a substitute for a court-registry status search.

Disclaimer: General legal education only. The analysis is not advice on any particular dispute and should be read with the judgment, applicable statute and subsequent case history.

Disclaimer — Bar Council of India

As per the rules of the Bar Council of India, advocates and law firms are not permitted to solicit work or advertise. This website is intended solely to provide general information about Candour Legal and its areas of practice, and is made available to the user only at the user's own specific request. The contents of this website do not constitute, and should not be construed as, legal advice, an advertisement, a solicitation or an invitation of any kind. Candour Legal assumes no liability for any action taken in reliance on the material on this website; readers facing a legal issue should seek appropriate professional advice on their specific circumstances. Use of this website, or transmission of any enquiry through it, does not create a lawyer-client relationship between the user and Candour Legal.

☎ Call 💬 WhatsApp Book Consultation

BEFORE YOU GO

Get a free 15-minute case assessment

Tell us what's going on and a Candour Legal advocate will call you back — no charge, no obligation.

Schedule my free assessment Call now